Monday, February 4, 2008

We are almost there ! Approaching F13E platform




Anchor handling operation commence at 0500 hrs till 2400hrs. Operation delay due to Strong Wind and Heavy Rain. Anchor No.4 found dragging during pre-tensioning. West alliance start to move tender towards the platform from 4th/0001hrs. Hopefully the weather permit us to Rig Up!!! Present Weather Wind NE x 17 knots, Swell Height 1.5m, Heel : 1.5 degrees and pitch : 1.0 degree.