Today's Event,

  1. Back ream to in side 18 5/8 to 2160ft, Circulate hole clean, POOH rack BHA, Wireline logging cancelled.( Oh dear how sad nevermind).
  2. MV Bourbon Alexandra along side, Pulled off location due to one engine failure, Report from captain, received bad fuel from labuan, "joint the club" .
  3. Rig up to Run 13 3/8" Csg, From 0115hrs-0345hrs 05.01.08.
  4. Trouble shoot TDS fault,change firing Card and Master card, TDS up and running.
  5. Make up (DWCS) Drill with Casing spear, Plan ahead: Run, land and cement 13 3/8" casing.