Let me have a go Saging, you mark off the csg tally, I'll show you how to run 13 3/8" Casing, a womens touch.
MV Bourbon Alexandre has cleaned her fuel tank, transfered clean fuel to her main tank, along side with cargo and back load. Departed for labuan 0530hrs 06.01.2008.Captain has instructed his crew to stand by on the oars, ETA Labuan 6 years.
Operations: Run land and cement 13 3/8" casing, Test casing to 3000psi.
Plan ahead: Wellhead work, Change BOPs from 21 1/4" to 13 5/8", Nipple up same with RCD for 12 1/4" Hole section.