Operations: Rig down casing equipment, Jet well head, Set and test Packoff, Nipple down 21 1/4" BOPs, Nipple up tubing head spool. Shut in wells 102 and 103 for heavy lifting.

Skid Rig, Change out BOPs, Lift 21 1/4" BOP from Platform to tender, 13 5/8" BOP from tender to platform, Nipple up 13 5/8" BOP and RCD.

Highlight of the day: Sunday night BBQ.

Plan ahead: Continue to nipple up Function test BOPs RCD, Connection test BOPs and perform accumulator test, M/u 12 1/4" BHA.