Thursday, June 26, 2008

The Eagle has landed on E11 Platform, well done !!!

Remaining secondary anchors were run on Tuesday 24th June completedpretension @ 1420hrs. Wait on Platform to shut down.
25th June @ 0500hrs platform commence shut down, 0900hrs Make finalapproach to heavy lift position, Transfer rig crews and make preparatory work for heavy lifting. 1345 hrs commence Heavy lifting, all lifts except Mast, 1900hrsprepare DES for Mast lift.
26th June @ 0035 hrs, the Eagle has landed. Heavy lifting completed.