Showing posts with label Heavy Lifting. Show all posts
Showing posts with label Heavy Lifting. Show all posts

Thursday, November 27, 2008

Capt.Ray & the crews ready for show time

Capt.Ray and the deck crews ready for rig-up heavy lifting

show time begin leading the way




Thomas ready with the Hammer!

Menjaya,Saging & Chio - lepak


Aling,Erwan & Mohd Firdaus the iron man

Wednesday, November 26, 2008

Tuesday, October 7, 2008

Good Bye E11 Platform

Marine Manager Capt.Andrew Cheah
Anchors Handling by Maersk Supplier

Anchors Handler - Maersk Supplier



Thank You & Good Bye E11 Platform



Monday, September 29, 2008

Ready for Rig Move

Empty deck ready for rig down ( Heavy lift )

Thursday, June 26, 2008

The Eagle has landed on E11 Platform, well done !!!

Remaining secondary anchors were run on Tuesday 24th June completedpretension @ 1420hrs. Wait on Platform to shut down.
25th June @ 0500hrs platform commence shut down, 0900hrs Make finalapproach to heavy lift position, Transfer rig crews and make preparatory work for heavy lifting. 1345 hrs commence Heavy lifting, all lifts except Mast, 1900hrsprepare DES for Mast lift.
26th June @ 0035 hrs, the Eagle has landed. Heavy lifting completed.

Sunday, June 22, 2008

Heavy lifting completed safely




Commence Heavy lifting Saturday 21st June @ 1305hrs.
Lift Mast fromfront on Hight tide and Good weather.
All lifts on tender@ 1900 hours, well done to all, Clean up platform through the night.

Monday, February 25, 2008

Sunday, February 24, 2008

Lifting Mast Set today???



Present weather : Swell : 1.0m and Heel : 1.0 degrees.

Tuesday, February 12, 2008

Attempt to Land Mast Set on F13E Platform


  • Attempt to lift Mast Set at 0810hrs.
  • Mast Set unable to land on the platform and returning to tender at 0840hrs.
  • Continue wait on weather, wind gusting NE x 20knots, swell 2.0m, Heel 1.5 degrees and Pitch 1.0 degrees.

Monday, February 4, 2008

We are almost there ! Approaching F13E platform




Anchor handling operation commence at 0500 hrs till 2400hrs. Operation delay due to Strong Wind and Heavy Rain. Anchor No.4 found dragging during pre-tensioning. West alliance start to move tender towards the platform from 4th/0001hrs. Hopefully the weather permit us to Rig Up!!! Present Weather Wind NE x 17 knots, Swell Height 1.5m, Heel : 1.5 degrees and pitch : 1.0 degree.

Sunday, February 3, 2008

Approaching F13E Platform






  • 0600 Commence anchor handling.


  • 0610 Anchor buoy no.6 on Bourbon Alexandre deck.


  • 0634 Anchor no.6 off bottom.


  • 0635 Anchor no.6 on stern roller, commence heaving anchor wire no.6.


  • 0650 Commence deballast to Field Transit draft.


  • 0732 Anchor no.6 racked.


  • 0740 Pennant wire no.6 secured to tender.


  • 0745 Stopped deballast - draft @ 7.30m.


  • 0800 Lewek Pelican arrives on location.


  • 0802 Anchor buoy no.2 on Bourbon Alexandre deck.


  • 0818 Anchor no.2 off bottom.


  • 0821 Anchor no.2 on stern roller -commence heaving anchor wire no.2.


  • 0827 Stopped heaving no.2 anchor wire no.2 - align spooler.


  • 0833 Resume heaving anchor wire no.2.


  • 0840 Stopped heaving anchor wire no.2 - bolt on spooler cover sheared, mechanic change out new one.


  • 0915 Resume heaving anchor wire no.2.


  • 0925 Stopped heaving anchor wire no.2 - problem with spooler, mechanic rectify problem.


  • 1005 Anchor buoy no.7 on Pelican deck.


  • 1013 Resume heaving anchor wire no.2.


  • 1030 Anchor no.7 off bottom.


  • 1035 Anchor no.7 on stern roller - commence heaving anchor wire no.7.


  • 1056 Anchor no.2 racked.


  • 1105 Pennant wire no.2 secured to tender.


  • 1115 Anchor buoy no.3 on Bourbon Alexandre deck.


  • 1117 Anchor no.7 racked.1125 Pennant wire no.7 secured & pick up 1 x anchor buoy.


  • 1130 Anchor no.3 off bottom.


  • 1132 Anchor no.3 on stern roller - commence heaving anchor wire no.3.


  • 1135 Lewek Pelican proceed to anchor buoy no.8.


  • 1148 Anchor buoy no.8 on Lewek Pelican deck.


  • 1157 Anchor No.8 off the bottom.


  • 1204 Anchor No.8 on stern roller, commence heaving anchor wire No.8.


  • 1210 Anchor No.3 racked.


  • 1220 Pennant wire No.3 racked.


  • 1221 Bourbon Alexandre on starboard, retrieving 3 anchor buoys on board West Alliance.


  • 1242 Anchor No.8 racked.


  • 1248 Pennant wire No.8 racked.


  • 1330 Forward Tow Bridle connected to Lewek Pelican, commence paying out Towing wire.


  • 1336 Towing wire attained 200m in length.


  • 1342 Anchor Buoy No.5 on deck Bourbon Alexandre.


  • 1356 Anchor No.5 off the bottom.


  • 1358 Commence heaving anchor wire No.5.


  • 1400 Anchor No.5 on stern roller Bourbon Alexandre.


  • 1450 Anchor No.5 racked.1


  • 505 Pennant Wire No.5 racked.


  • 1530 Anchor Buoy No.1 on deck Bourbon Alexandre.


  • 1544 Commence heaving anchor wire No.4.


  • 1545 Anchor no.1 off the bottom.


  • 1548 Anchor No.1 on stern roller, commence heaving anchor wire No.1.


  • 1620 Anchor No.1 racked.


  • 1628 Pennant Wire No.1 racked.


  • 1639 Anchor Buoy No.4 on deck Bourbon Alexandre.


  • 1652 Anchor Buoy No.4 off the bottom.


  • 1654 Anchor No.4 on stern roller, continue heaving anchor wire.


  • 1718 Anchor No.4 racked.


  • 1730 Pennant Wire No.4 racked.


  • 1735 Lewek Pelican increase power slowly.


  • 1752 Bourbon Alexandre recovering supply boat LCT mooring and will proceed to F13E to deploy.


  • 1757 Attained 500m Towing length.


  • 1800 Commence Towing to F13E.


  • 1803 Bourbon Alexandre recovered LCT Buoy, found mooring rope broken and one of th buoy damaged.

Saturday, February 2, 2008

Highlight of the Day


  • 1238 Anchor Buoy No.8 on deck Lewek Snipe.
  • 1250 Anchor No.8 off the bottom.
  • 1255 Anchor No.8 on the stern roller.
  • 1257 Commence paying out Anchor wire No.8.
  • 1312 Stopped paying out wire, Anchor No.8 on the bottom.
  • 1322 Anchor Buoy No.8 in the water.
  • 1400 Lewek Snipe departure & proceed to Labuan. Commence moving tender to lifting position.
  • 1435 Distance to Platform = 35ft.
  • 1448 Attained Lifting Position.
  • 1548 Commence Heavy Lifting, Rig Floor Package off the platform ( 133MT ).
  • 1556 Rig Floor Package landed on tender.
  • 1715 Master Skid off the platform ( 159MT ).
  • 1730 Master Skid landed on tender.
  • 1915 All crew from Platform return on tender.
  • 1930 Commence moving tender to stand off position.
  • 2010 Stopped moving tender, attained stand off position. Informed Bourbon Alexandre to standby for Anchor Handling on 2nd/0600hrs.
Lewek Snipe Near Miss Incident
Lewek Snipe was sent to Labuan after anchor handling on E8 for Investigation. How Lucky She is, the anchor wire stopped by the stopper bar to prevent the wire slide towards forward of her deck !

Friday, February 1, 2008

E8 Rig Down



  • 0300 Resume moving tender to side lift position.

  • 0400 Completed moving tender to side lift position.

  • 0844 Mast Set off the E8 Platform (106MT).

  • 0857 Mast Set landed on tender.

  • 0930 Drawwork off the platform (60MT).

  • 0935 Drawwork landed on the tender.

  • 1031 Koomey cantilever off the platform (100MT).

  • 1041 Koomey Cantilever on the tender.

  • 1110 Off Driller Cantilever off the platform (43MT).

  • 1116 Off Driller Cantilever on the tender.1

  • 141 Mud Tank Package Off the Platform (68MT)

  • 1146 Mud Tank Package on the tender.

  • 1310 Commence moving tender to drilling position for front lift.

  • 1345 Anchor Buoy No.7 on deck Lewek Snipe.

  • 1354 Anchor No.7 off the bottom.

  • 1400 Anchor No.7 on the Stern Roller, commence heaving anchor wire No.7.

  • 1510 Stopped heaving anchor wire No.7.

  • 1525 Resume heaving anchor wire No.7.

  • 1554 Anchor No.7 racked, pennant retrieved on board west alliance.

  • 1555 Commence moving tender to drilling position for front lift.

  • 1718 Pennant Wire No.7 transffered to Lewek Snipe.

  • 1820 Commence paying out Anchor wire No.7.

  • 1840 Stopped paying out anchor wire No.7.

  • 1848 Anchor No.7 on the bottom.

  • 1900 Anchor Buoy No.7 in the water.

  • 2036 Anchor buoy No.8 on deck.
  • 2052 Anchor No.8 off the bottom.
  • 2056 Anchor No.8 on deck Lewek Snipe, comemnce heaving anchor wire No.8.
  • 2156 Anchor No.8 racked.
  • 2204 Pennant Wire No.8 retrieved.
  • 2210 Anchor Handling operation stopped due to strong wind and current(1.8 knots). Continue to move tender towards westerly side.
  • 2250 Stopped moving tender.

Thursday, January 31, 2008

On our way to Side Lift !!!


  • West alliance with 8 anchors on the bottom, preparing for Side Life.
  • Patrick stopped winching and stand off 200 feets east of the E8 Platform due to electrical problem.
  • Electrician troubleshoot Anchor Winch 7 & 8 from 30th/1830hrs.
  • Lewek Snipe standby on location.
  • Wind NE x 7 - 10 knots, Swell height 1.0m, Rolling : 1.0 degress occasionally, Heave : 0.5m.

Sunday, December 23, 2007

We are all Done !!!

West Alliance back on drilling position !! Mast Set successfully landed on E8 Platform at 23.12.2007, 1330hrs.

Sunday, December 16, 2007

West Alliance moving for Side Lift

West Alliance unable to rig up Mast Set due to the height of the platform. Commence Anchor Handling at 0300hrs by Bourbon Alexandre.

Heavy Lifting on E8 Platform




Master Skid, Rig Floor Package, Koomey Cantilever, Mud Tank package, Off Driller Cantilever and Drawwork successfully landed on E8 Platform.
One more to go - Mast Set!! We are waiting for High Tide at 0100hrs !






Thursday, December 13, 2007

Exciting Moment......

Watching the Shooting Star? Hey guys, go to sleep !